{"id":42945,"date":"2019-05-07T14:28:16","date_gmt":"2019-05-07T18:28:16","guid":{"rendered":"https:\/\/fondationrivieres.org\/?p=42945"},"modified":"2023-04-07T13:18:20","modified_gmt":"2023-04-07T17:18:20","slug":"lettre-melcc-securite-barrages","status":"publish","type":"post","link":"https:\/\/fondationrivieres.org\/en\/lettre-melcc-securite-barrages\/","title":{"rendered":"Letter to the Ministry of the Environment and the Fight against Climate Change: Dam safety"},"content":{"rendered":"

Montreal, May 7, 2019
TRANSMISSION BY EMAIL<\/p>\n\n\n\n


<\/p>\n\n\n\n

Mr. Benoit Charette, Minister
Ministry of the Environment and the Fight against Climate Change
Marie-Guyart Building
675, boulevard Ren\u00e9-L\u00e9vesque Est, 30e<\/sup> floor
Quebec (Quebec) G1R 5V7<\/p>\n\n\n\n

<\/div>\n\n\n\n

Subject: Dam safety \u2013 Delays in securing hydroelectric power stations<\/h2>\n\n\n\n

<\/p>\n\n\n\n

Minister,<\/p>\n\n\n\n

The recent last-minute evacuation of residents of Grenville-sur-la-Rouge, threatened by the rupture of the dam at the Bell power station, owned by Hydro-Qu\u00e9bec, once again highlights the importance of ensuring sound management of works. The Dam Safety Act is supposed to assume most of the governance, ensure the safety of the population and preserve capital assets, but following this event, we checked what is happening with the others hydroelectric power stations. We were able to note gaps in its application. <\/p>\n\n\n\n

According to the Directory of Dams that we consulted, the production and approval of reports assessing the safety of structures and the implementation of corrective measures are experiencing worrying delays for around forty installations in Quebec. These delays sometimes exceed 10 years and are noted at the different stages of control provided for in the Law:<\/p>\n\n\n\n